Southern England WtE update

The last few weeks have seen mixed fortunes for several major waste-to-energy projects in the South of England. Here’s a roundup.

On 27th September 2019, Grundon and Viridor announced outline plans for the development of a new waste-to-energy (WtE) facility at Ford in West Sussex. The facility will be built at Grundon’s Ford Circular Technology Park, near its existing waste transfer and depot operations, and adjacent to Viridor’s existing materials recovery facility (MRF).

Attempts to build a facility on the site go back several years. West Sussex County Council granted planning permission for a non-hazardous waste facility on the site in 2014, but this was never built. While Grundon has noted that the planning permission therefore already exists for the site, it is currently unclear how the 2019 proposal relates to the older plans. The latter entailed a 200,000 tonne per year gasification plant, dealing predominantly with industrial and commercial waste.

Click here to view the precise location in Bing maps.

map

Also in the south of England, Wheelabrator has experienced a setback in its attempts to construct a WtE plant at the A303 Enviropark near Andover in Hampshire. A public consultation ended in March 2019. Wheelabrator expects the second stage of statutory public consultation to take place between early November to mid-December 2019, later than originally planned. Wheelabrator has been reviewing the design plans of the proposed development after receiving feedback on the current design during non-statutory consultation and has confirmed that there will be two combustion lines at the outset, and therefore there will be no phasing. The planning application is expected to be submitted towards the end of the first quarter of 2020.

Click here to view the precise location in Bing maps.

map2

Finally, there is progress to report on the long-anticipated replacement for the Edmonton WtE plant in north London. This dates to the 1970s and is coming to the end of its working life. The operator, North London Waste Authority (NLWA), first began plans for a new facility in 2014. Contracts began to be issued in 2018, and a third ‘Market Information Event’ was held on 9th October 2019 in central London for works associated with the delivery of the project. It has been subject to some ground preparation delays, but NLWA still anticipates that the site will become operational in 2025.

Click here to view the precise location in Bing maps.

map3